eoelker - posted 11:57, Saturday 05 September 2026 (12245)
E-Recycle Load from LASTI Control Room

I'm trying to clear out the computer graveyard in the LASTI control room so we have sufficient workstation desks when the coupled cavity experiment ramps up.

 

I plan to schedule an E-recycle pick up with MIT for the week of Sept 21 to give folks time to identify any hardware in the NW17 hallway they would like us to keep. 

 

 

Computer hardware to recycle

Here's what I moved to in front of the freight elevator for pickup:

 

Item            Estimated Purchase date

SunBlade 1500:        2002

SunFire X220 (2x):    2006

SunBlade 100:  2001

Thinkmate U1 Server:  Unknown

4x Slow control Servers from PDE Expt:  Unknown (likely earlier than 2007)

Dell Inspiron 530 Desktop (4x):  2007

old Non-widescreen monitors (4x)

1st Generation PDE Front End machine:  Unknown   (this was not the front end at the end of the expt's lifecycle, i am saving the newer front end machine)

Old D-space DAQ:  Unknown

 

Computer hardware to keep

Below are the Items I decided to keep.  Still old, but we're running low on computers to use as CDS workstations so we need to keep something

Item                Estimated Purchase Date

Dell Optiplex 3010:  2012

Lenovo ThinkServer TS140:   2013

Lenovo ThinkStation E30:   2011

(old CDS front ends) Supermicro U2 Rackmount Server (2x):   2010     Note: There are 2x more of these in the racks in the highbay

6x  Widescreen monitors

 