mrtodd - posted 17:17, Friday 14 August 2026 (12221)
MID-Y HAM and Y HAM optic shuffle
Mitchell R, Matthew T, Eric O

We spent the morning realigning the input beam going into the MID-Y HAM to recover the REFL alignment that was previously achieved. This was because somehow one of the mirrors was moved without anyone's knowledge. At 300mW input power we were able to get around 90mW at REFL. The input coupler is quoted for 90% reflectivity at 45deg, which could explain the lower power at REFL, given the input coupler is at normal incidence.

The afternoon was spent fetching optics and mounts from the MID-Y HAM to have for the output coupler and output steering optics. The plan is to put the high reflector into one of the mounts and use that for the output coupler, and try to see if we can align the cavity axis to see some flashes.