SQZ General
eoelker - posted 17:07, Sunday 22 February 2026 - last comment - 19:36, Tuesday 03 March 2026(12144)
Slow Controls reanimation progress

In order to restore the automation for the LASTI Squeezer, we need to revive many of the slow controls features that havent worked since the days of the 16m FC experiment.  Below is a list of what needs to be done and the current status

Subsystem application Current status
MEDM/EPICS interface for synthesizers Intensity controls for CLF and LO paths, Phase shifts for CLF 1F and 2F loops All required synthesizer interfaces are working again except for one 2-channel Marconi
Picomotor waveplate controller  Intensity controls for Seed and Pump paths EPICS CA Driver is working, but IP address isnt set correctly: cannot ping
Beckhoff TEC Controller OPO Temp control for in-vacuum use Working again! See Daniel's post for details
Flipper controls block/unblock paths for different measurement configurations Beckoff channels working again! Still need to track down short in flipper power supply
Camera capture card OPO 532 trans, SHG trans, OPO 1064 trans, PMC trans monitors Not working, not sure why.
Guardian Automation of SQZ locking and measurements Not working.  Jamie Rollins is visiting this week (weather permitting)
Beckhoff Aux channels Monitors of power levels, etc Corresponding beckhoff rails are working again.  Still need to test through to EPICS
Slow EPICS channels -> Framebuilder Logging monitor channels, trending back values, etc. Not working.  Jamie Rollins is visiting this week
New CDS workstation Workstation for the cleanroom. Working!  Just need to move from control room into high bay

Other than the Guardian and the framebuilder stuff, we're most of the way there. Hopefully Jamie Rollins can help us when he visits this week (hopefully his flights don't get cancelled!)  

I'm sure someone else in the group has done camera capture with linux -> MEDM and can help us debug.

Comments related to this report
eoelker - 19:36, Tuesday 03 March 2026 (12152)

More progress on this:

Fixed the flippers yesterday:  There was a blown protection diode that was shorting out our +24V sorenson.  Fixed that, now everything is happy

Synthesizers:  Got the last one working.  Reshuffled the synths a bit: Now the SG380 synthesizers live the rack and we have the ability to set the phase offset directly with these for the CLF1F and CLF2F demodulation.

Picomotors:  Got the waveplate controller working today.  I plan to move them on the table s/t one controls the seed power and one controlls the pump power.  We no longer need a pair of motorized waveplates right before the pump fiber since the fiber is now PM.