Heisenberg IFO General
hudsonl - posted 15:51, Thursday 08 January 2026 (12130)
Heisenberg Marconi Cabling
Daniel and I removed some cables from Marconis used to actuate AOMs in the Heisenberg setup so we could use them temporarily to measure fiber phase noise for the OEO project. The cables for each marconi are cable-tied together and labeled according to which port they should be plugged back into to run the Heisenberg experiment. The images attached show the proper settings on the Marconis for the Heisenberg experiment. The devices should be returned to these settings when we return to collecting data on the Heisenberg experiment.