[Wen, Eric]
We found a number of spare Class-A fiber collimators in the orange lab, and plan to use them to assemble the new VOPO 10 dB setup in the VOPO tank. These are of the O3 variety, so are no longer as useful as site spares (the spares page has been updated).
We plan to implement an existing layout solution for the CLF and 532 injection paths for the VOPO cavity (with tweaks for fiber collimator measurement). After some digging on the DCC we were able to find the desired documentation:
- VOPO preliminary design doc has a mode matching solution for both paths CLF path. It appears that the pump path solution was NOT used and the exact positions for the CLF optics were a little different in practice. We'll follow the spreadsheet and layout documents below for the CLF path. We will follow this document for the pump path, since we don't have any -75 mm ROC lenses and cannot implement the pump path solution used at the sites in O3.
- VIP Layout v5 shows the layout used in HAM6 during O3. The description in the DCC page has the exact positions of the lenses and collimators relative to the cavity. We will copy this CLF path.
- This spreadsheet has a components list from the assembly during O3. This states the ROC for the various lenses. The ROC for the pump path lenses is differend from what is in the preliminary design doc.